Project Overview
The project will include placement of conduits for broadband infrastructure, and potentially pedestrian and/or bicycle amenities along Red Dog Road from Boulder Street to approx. Pasquale. PG&E will be the lead design on this project. The County has approximately $6,100,000 is Rule 20A credits that are to be used for the undergrounding of existing utility lines.
Schedule
Estimated 2028
Current Status
- Undergrounding District - Formed and Approved
- Design coordination underway with PG&E
Funding
Funding is through Rule 20A Funds.
Environmental Review
Contact Information
Nevada County Department of Public Works - Engineering Division (530) 265-1411
Special Notices