Project Summary
This 5-year road maintenance and rehabilitation plan will resurface or repave roads throughout Nevada County. Roads are selected and prioritized based on the County’s Pavement Management System to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment. The plan includes various potential pavement preservation and replacement techniques. Work to be done includes asphalt overlays, micro surfacing, a/c dike installation, striping, and other repairs as necessary.
Schedule
Work is to begin September 2, 2025, through mid-October.
Roads Affected by the Project
- McCourtney Rd: Between Larkspur Lane and Indian Springs Rd
- Indian Springs Rd: Near Vineyard Ln
- Spenceville Rd: Near Penn Valley Dr
Prepare
Please be prepared for up to 20-minute delays from 7:00 am - 7:00 pm Monday through Friday due to one-lane traffic controls. Motorists will have access throughout construction, and message boards will be placed 72 hours before construction to allow residents to plan accordingly.
Current Status
Dates | Road Work Anticipated | Photo |
|---|
Anticipated Start Date September 2025 | The Contractor's Crews will be on - McCourtney Rd
- Indian Springs Rd
- Spenceville Rd
|  |
Funding
Stay Informed
Contact
- Nevada County Department of Public Works - Engineering Division (530) 265-1411
- Submit a road maintenance request to report drainage concerns, potholes, and more at www.NevadaCountyCA.gov/ServiceRequest.